SP phases 20, 21 operational by mid-March

SP phases 20, 21 operational by mid-March
Iran is to launch phases 20 and 21 of the supergiant South Pars Gas Field by mid-March 2017.

Managing Director of Oil Industries' Engineering and Construction Group (OIEC) said the phases will go on-stream with a daily production capacity of 50 mcm of natural gas, Shana reported.
Behzad Mohammadi said that the phases will become fully operational in view of the accelerated progress of drilling operations at the onshore and offshore sections of the phase developments.
"Drilling operations in 11 wells of Phase 21 will be complete within a month while 11 wells in Phase 20 will be concluded by mid-summer," said Mohammadi.
The OIEC chief further said topsides of the two phases will be fully installed at designated spots by the end of autumn or late-December.
He also said gas can be extracted from 16 wells of 22 wells of the two phases.


May 15, 2016 10:21
iran-daily |

Comments


Sender name is required
Email is required
Characters left: 500
Comment is required


تصویر نمادالکترونیکی

About Us

The section of oil, gas and petro-chemistry is the up-most and first industrial vantage of the country and the pivot of the Economy of Iran. Regarding the importance of this section and the need for coordinating and organizing the most active people in the field of production and exporting oil ,gas, and petrochemical products ,some forethoughtful and job- makers in the private section of the country decided to come together to fight against the threats by using the opportunity of mass intelligence and potentials.